W.6_ESY_Comparison of Mutually Exclusive Projects by B-C Ratios


Taking master degree or study on the subject of urban horticulture has been one of my life aspirations. However due to work constraint, to be able to decide on which university selected is depending with many consideration.   Problem Definition¬† … Continue reading

Posted in Tak Berkategori | 1 Comment

W08_RD_Team Float Analysis


Problem Recognition, Definition, and Evaluation Garuda AACE 2015 weekly report contains several information related with the achieved progress and its plan, however after several weeks, Team facing difficulties in controlling as well monitoring and reporting progress in detail level. Float … Continue reading

Posted in Tak Berkategori | 1 Comment

W8_AAA_Benefit Cost Ratio Oil Project Development


Problem Definition Following previous blog (W6), the company will evaluate the project economic using Benefit Cost Ratio then compare both projects and choose the best project that give High value of Benefit Cost Ratio. Identify the Possible Alternative The project … Continue reading

Posted in Tak Berkategori | 2 Comments

W10_WW_ ERR of Oil Field Development Project


1. Problem Definition Following previous case study on W9 blog posting, after deciding to run 3D seismic acquisition and develop Bravo field, the company need to calculate the return of the project using External Rate of Return (ERR). 2. Identify … Continue reading

Posted in Tak Berkategori | 2 Comments

W9_EY_Estimating Process Benchmark


Problem Definition Follow up the suggestion in W5 blog posted by Author with regard to benchmark the estimating process to US Government Accountability Office (GAO) with the current Author Estimating process application. Author will do the best practise check list … Continue reading

Posted in Tak Berkategori | 3 Comments

W08_WRP_Integrated Cost and Schedule Risk Analysis


1. Problem Definition The Interstellar Oil Company is intended to build a mini LPG plant Andromeda gas field. Cost Estimator and Scheduler has put contingency-free cost of US$ 650 million for 820 days of completion. Management is concern about what … Continue reading

Posted in Tak Berkategori | 4 Comments

W07_RD_Team Workloading Histogram


Problem Recognition, Definition, and Evaluation After several week, Team now have sufficient data that can be used to analyze team performance in order to help team to re-align with the plan that have to be completed. However before proceed to … Continue reading

Posted in Tak Berkategori | 1 Comment