W15_HMIP_Determine appropriate MARR for PT ABC using PERT Analysis in Indonesia


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to determine the reliable MARR. Since the MARR = 20% seems not suitable with current oil & … Continue reading

Posted in Tak Berkategori | 1 Comment

W14_HMIP_ Project Portfolio Management using Analytical Hierarchy Process (AHP)


Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to execute all of them as fast as possible as per time schedule. In the other else, the … Continue reading

Posted in Tak Berkategori | 3 Comments

W14_EY_Mechanical Equipment Procurement Cost Database Development


Problem Definition For our internal cost estimate database development, Author requested by Estimating Manager to collect the estimating data from previous project. One of the focus is to collect equipment cost and develop cost relationship based on the equipment parameter … Continue reading

Posted in Tak Berkategori | 2 Comments

W13_HMIP_ Project portfolio analysis using PW, AW and FW


Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to add estimated reject rate between each alternative and do project prioritization using PW, AW and FW between … Continue reading

Posted in Tak Berkategori | 1 Comment

W13_HI_Exercise for Team Re-baseline


  Problem Definition Continue from blog W11 and W12, in Garuda AACE 2015 Project, on Week 10, the Author and 4 other members, submitted Change Order (CO) to Client for descoping Paper Project. The Client accepted the CO with notes … Continue reading

Posted in Tak Berkategori | 3 Comments

W.8_ESY_5 Why Root Cause Analysis for Main Cost Deviation


After one project is being completed during Project Closing Phase, Project Manager is required to ensure that the lessons learned and best practices are being captured. These documents are being used as a feedback to the Solution Manager (looped back … Continue reading

Posted in Tak Berkategori | 1 Comment

W13_WRP_Further Economical Evaluation on MRU using POT


A. Problem Recognition Following previous blog posting W06.1_WRP_MRU Preliminary Economical Evaluation using NPV and W10 using B-C Ratio, on this blog the selection will be analyze further using Pay Out Time. B. Feasible Alternatives From blog W03, it is obvious … Continue reading