Monthly Archives: July 2015

W16_WW_Cost Analysis of Critical Spare Compressor


1. Problem Definition Garuda Energy Company, a PSC Oil & Gas Company, conducted an assurance review for a gas field development project. From the review, the company found that there is no spare of gas compressor which is critical equipment. … Continue reading

Posted in Tak Berkategori | 1 Comment

W20_EY_Cost Budgeting for Class 2 Cost Estimate Preparation Effort


Problem Definition As one part of project development phase requirement to have the next step of cost estimate update for CAPEX Class 2 estimate. Author need to budgeting the cost for class 2 cost estimate. This information will use to … Continue reading

Posted in Tak Berkategori | 1 Comment

W15_WW_ Sensitivity Analysis of Field Development Project


1. Problem Definition Following my W8 blog, in order to analyse the influences of economic input (reserves, oil price, opex & capex) to the project economic calculation, Garuda Energy Company, a PSC Oil & Gas Company, need to run sensitivity … Continue reading

Posted in Tak Berkategori | 1 Comment

W19_EY_Work Breakdown Structure (WBS) Development for CAPEX Cost Estimate


Problem Definition As part of cost estimating plan, before to develop cost estimate one thing that must be develop is Work Breakdown Structure (WBS). Based on this requirement Author will develop the WBS to accommodate CAPEX class 2 cost estimate … Continue reading

Posted in Tak Berkategori | 2 Comments

W19_AAA_Blogs Project’s Schedule Analysis (Earned Value Management Part I)


1. Problem Definition Garuda team has reach the 19th blog posting in Week 19 and the project manager will evaluate the performance of current project using Earned Value Management (EVM) such as SPI, CPI, SV and CV and also give … Continue reading

Posted in Tak Berkategori | 2 Comments

W14_WW_Cost Estimation of Preparation Effort


1. Problem Definition Garuda Energy Company, a PSC Oil & Gas Company, needs to produce a Class 4 Estimate in the end of their Feasibility Study on Ranau field development project. The Company plan to engage Contractor to deliver the … Continue reading

Posted in Tak Berkategori | 1 Comment

W20_HMIP_ Sensitivity Analysis on Project A,B and E in PT ABC.


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to conduct Sensitivity Analysis of Project A, B and E in order to more comprehend of project … Continue reading

Posted in Tak Berkategori | 1 Comment