Author Archives: harnadiirawan

W25_HI_Lesson Learned from Garuda AACE 2015 Class


Problem Definition Our Garuda AACE 2015 Class is about to finish. This blog is to present any feedback during the class that can be useful lesson learned for the next class(es). Development of Feasible Alternatives The main topics for this … Continue reading

Posted in Tak Berkategori | 1 Comment

W24_HI_Cost Estimating Method


Problem Definition Company A, a PSC Oil & Gas Company, is evaluating the development of a new gas field development. Strategic management decision in the preliminary screening stage shall be taken considering many aspects. One of the critical aspects is … Continue reading

Posted in Tak Berkategori | 3 Comments

W23_HI_Analytic Hierarchy Process


Problem Definition In this blog, I would like to analyze the same case study as in my previous W3 Blog, bid evaluation, using Analytic Hierarchy Process (AHP), and comparing the result. Development of Feasible Alternatives Based on W3 Blog, the … Continue reading

Posted in Tak Berkategori | 2 Comments

W22_HI_Equipment Factored Estimate (Part 2 : Wroth Method and Chilton Method)


Problem Definition Continue the case from W21 Blog, Company A, a PSC Oil & Gas Company, needs to produce a Class 4 estimate for one of their projects. The Project Team has set up a preliminary equipment list of the … Continue reading

Posted in Tak Berkategori | 1 Comment

W21_HI_Equipment Factored Estimate (Part 1 : Lang Method and Hand Method)


Problem Definition Company A, a PSC Oil & Gas Company, needs to produce a Class 4 estimate for one of their projects. The Project Team has set up a preliminary equipment list of the process plant. Refer to Cost Estimate … Continue reading

Posted in Tak Berkategori | 2 Comments

W20_HI_ERR of Field Development


Problem Definition Continue the case study from W18 Blog, after move forward with the base case option, the Company need to calculate the return of the project using External Rate of Return (ERR). Development of Feasible Alternatives Based on previous … Continue reading

Posted in Tak Berkategori | 2 Comments

W19_HI_Developing Labour Rates


1. Problem Definition Company A, a PSC Oil & Gas Company, is developing a project in remote area in Indonesia. The Company needs to import civil skilled labours for daily work on site facilities during pre-operation stage. Company invites then … Continue reading

Posted in Tak Berkategori | 4 Comments