Author Archives: herymadapaska

W25_HMIP_Earned Value Management Probabilistic Forecasting using Monte Carlo Simulation of Project A in PT ABC.


1. Problem Definition Continue from Blog W21 after choosing Project A using Monte Carlo Simulation. Project Manager of PT ABC were requested by CEO to Earned Value Management calculation using Monte Carlo simulation of Project A in order to more … Continue reading

Posted in Tak Berkategori | 1 Comment

W24_HMIP_Integrated Cost & Schedule Risk Analysis using Monte Carlo Simulation of Project A Cost & Schedule in PT ABC.


1. Problem Definition Continue from Blog W21 after choosing Project A using Monte Carlo Simulation. Project Manager of PT ABC were requested by CEO to conduct Integrated Cost & Schedule Risk Analysis of Project A in order to more comprehend … Continue reading

Posted in Tak Berkategori | 2 Comments

W23_HMIP_Schedule Risk Analysis using Monte Carlo Simulation and PERT Analysis Method of Project A Schedule in PT ABC.


1. Problem Definition Continue from Blog W21 after choosing Project A using Monte Carlo Simulation. Project Manager of PT ABC were requested by CEO to conduct Schedule Risk Analysis of Project A Schedule in order to more comprehend of project … Continue reading

Posted in Tak Berkategori | 1 Comment

W22_HMIP_Benefit Cost Ratio Analysis on Project A, B and E in PT ABC.


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to conduct Benefit Cost Ratio Analysis of Project A, B and E in order to more comprehend … Continue reading

Posted in Tak Berkategori | 1 Comment

W21_HMIP_Monte Carlo Simulation Analysis on Project A, B and E in PT ABC.


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to conduct Monte Carlo Analysis of Project A, B and E in order to more comprehend of … Continue reading

Posted in Tak Berkategori | 1 Comment

W20_HMIP_ Sensitivity Analysis on Project A,B and E in PT ABC.


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to conduct Sensitivity Analysis of Project A, B and E in order to more comprehend of project … Continue reading

Posted in Tak Berkategori | 1 Comment

W19_HMIP_ Determine Appropriate Depreciation Method on PSC of PT ABC.


1. Problem Definition Continue from Blog W10 after choosing Project A, B and E. Project Manager of PT ABC were requested by CEO to determine appropriate depreciation method on PSC. He need to determine which method is appropriate on executing … Continue reading

Posted in Tak Berkategori | 2 Comments