Author Archives: Wilson R. Pariangan

W25_WRP_Lesson Learned


1. Problem Definition There is always room for improvement and the next project should be better than the previous one if we learn about it. In line with that, Client would like us to write what we learn from the Garuda … Continue reading

Posted in Tak Berkategori | 1 Comment

W16_WRP_Production Facility Integration for Marginal Gas Fields


1. Problem Definition An oil and gas company discover some gas fields that not economic to be developed individually due to the amount of accumulation gas cannot satisfy the field economic. In addition, the most of the gas from those … Continue reading

Posted in Tak Berkategori | 1 Comment

W15_WRP_Problem Focus Using Pareto Analysis


Problem Definition An oil and gas company is reviewing the problems that leading to over budget and on-stream delay. They need to do pareto analysis for lesson learned for the next big project, on what problem that they need to … Continue reading

Posted in Tak Berkategori | 1 Comment

W14_WRP_Operational Cost Optimization


Problem Definition In order to make continuous improvement, Company launches Cost Optimization Campaign. The Company has some oil fields with associated gas that, if gathered, will build good accumulation to be utilized as fuel for the gas engine. Currently the … Continue reading

Posted in Tak Berkategori | 1 Comment

W13_WRP_Further Economical Evaluation on MRU using POT


A. Problem Recognition Following previous blog posting W06.1_WRP_MRU Preliminary Economical Evaluation using NPV and W10 using B-C Ratio, on this blog the selection will be analyze further using Pay Out Time. B. Feasible Alternatives From blog W03, it is obvious … Continue reading

Posted in Tak Berkategori | 2 Comments

W12_WRP_ Learning Curve Analysis on My Blog Posting Project


Problem Recognition As analyzed in W11 blog, author cannot afford to continue the paper project, therefore a de-scoping proposal for the paper project had been submitted and approved by Client on May 26. This should be follow with re-baselining proposal … Continue reading

Posted in Tak Berkategori | Tagged , | 1 Comment

W11_WRP_Estimate at Completion (EAC) – Paper Project


Problem Definition Paper project comes to critical path and author should decide whether to continue the paper project or descope it. To make the decision, author make analysis on how many resources required to finished the paper project within acceptable … Continue reading

Posted in Tak Berkategori | 1 Comment